‘How lawmakers constituency projects contravenes procurement act’ 

The Network for the Actualisation of Social Growth and Viable Development (NEFGAD), a public procurement advocacy group, has condemned the interference of the national assembly with budgetary allocations under the guise of constituency projects.

Akingunola Omoniyi, the head of the group, in a letter to President Bola Tinubu on Monday, said project initiation by the lawmakers is beyond the legislative powers of the national assembly as outlined in the Nigerian constitution and the Public Procurement Act 2007.

READ MORE: ANALYSIS: Budget padding, Ningi’s suspension, constituency projects largesse and burden of truth

He advised the president to take immediate action to address violations, noting that the “budget padding” has given the country a bad name.

“The legislative power of the national assembly is to make laws, and such power in itself is not without limit, particularly on public procurement,” the letter reads.

elsamad new

“The power had been sufficiently exercised by the enactment of the extant Public Procurement Act 2007, hence, any conduct of the National Assembly on public contracts outside of the extant Public Procurement Act/regulations amounts to abuse of power/over-legislation.

READ ALSO: Alleged Budget Padding: SERAP drags Akpabio to court over failure to recall Ningi

“The power to initiate any procurement proceeding is purely an executive function and lies with procuring entities/ministerial and extra-ministerial procurement committees and such must be conducted strictly in line with section 18 (a, b, c d, e, f and g) of the Public Procurement Act 2007.

“The provisions mandate procuring entities to engage in the planning of procurement to prepare the needs assessment and evaluation; identifying the goods/works or services required.

“The spirit and letter of the Public Procurement Act underscore the need to organise public procurement to ensure economy of scale, guide against undue interference and ensure that the process maintains a high level of proven system scrutiny and integrity. 

READ ALSO: Budget Padding: Senate to review Ningi’s three-month suspension- Akpabio

“Hence, any project/procurement item that does not satisfy legally outlined planning and organizational criteria (as in the case of constituency projects which are inserted midway into public procurement proceedings by the national assembly), is utterly defective.”